The duplex at Salmon Valley Baptist is nearing completion. The electrical work is completed, walls are finished, flooring is done, and baseboard is up. Cabinets are installed and appliances are in. The plumbers are currently completing their work.
We still need to put shelves in the pantry and the closet. We have to put some insulation in the crawl space. There is also some work needed on the exterior before we can call for inspection. We are hoping that the final inspections will be completed in May so that the building can be occupied.